Below is my editing schedule and I hope that with my organisational skills I will be able to follow it. I have scheduled it so each point is over 5 days, for example, when I start to put everything together right at the first stage, it says I have from the 5/1/15 till the 9/1/15 which gives me 5 days. The reason for this is because I thought I should be more realistic as I am most likely not going to get most of the editing done in a matter of a few days. So therefore, I have equally spread it out so that I have time to come back to it and change things, this also will prevent me from getting stressed and not following my editing schedule.
Day/week
|
What?
|
5/1/15 - 9/1/15
|
Edit the beginning adding on titles and other text
|
12/1/15 - 16/1/15
|
Basic plot with what footage will be where (in order)and then add colour filters if needed
|
19/1/15 - 23/1/15
|
Start editing these clips making them the right lengths and add transitions between clips if needed
|
26/1/15 - 30/1/15
|
Add on the music and any other sound effects (e.g. text tone, children laughing and car door slamming)
|
2/2/15 - 6/2/15
|
Finish and add on credits at end or any other text that is needed
|
9/2/15 - 13/2/15
|
Any other touch ups whether it being due to audience feedback or last minute changes
|